CDM 2007 Construction phase plan
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 construction phase plan, see Construction phase plan.
The Construction (Design and Management) Regulations 2007 (CDM regulations), required that on all notifiable projects, a principal contractor is appointed, and that they develop a construction phase plan setting out how health and safety will be managed during the construction of the project.
Notifiable projects are those which last more that 30 days or involve more than 500 person-days of construction work.
The client must not allow work on site to proceed unless a construction phase plan (CPP) has been prepared, at least for the early stages of the works, and arrangements for the development of the rest of the plan (including the incorporation of information from sub-contractors) has been established.
The construction phase plan should be specific to the project (rather than generic), concise and easy to understand (perhaps with explanatory photographs or drawings).
It might include:
- A description of the works.
- Contact details for those involved in the project.
- Roles and responsibilities.
- A description of existing information and where it can be found.
- The health and safety standards to which the works will be carried out.
- Communication, training and monitoring arrangements.
- Pre-construction issues.
- Arrangements for managing the works, such as security, traffic management, site rules and welfare arrangements.
- Assessment of risks.
- Arrangements for managing significant risks.
- Emergency procedures.
- Information about restrictions which may affect the work (such as restrictions imposed by the client).
- Arrangements for creating the health and safety file.
- Circumstances under which risk assessments or method statements should be prepared.
- Sources of other information.
A detailed list of the possible contents of the construction phase plan was published in appendix 3 of Managing Health and Safety in Construction Construction (Design and Management) Regulations 2007 Approved Code of Practice.
The construction phase plan is different from the health and safety file which is prepared by the CDM co-ordinator and provides information allowing future work to the building to be carried out safely.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Comments